Hello,

I send you the latest time table of the COLLECTOR WP (6 april 03).
 
In the pre-BENE phase there is the preparation of the Design Studies.

In the COLLECTOR time table, I have factorised the Join COLLECTOR & TARGET 
meetings in the  first part of the table and Vittorio agrees that it is more efficient to present 
like that.
In the second part of the table, there are key points:
1.	The Collector Test Area (CTA) proposal oct 2004: the idea is that after presenting the 
DS, we need certainly some preliminary R&Ds to be able to draw some reasonable 
CTA.
2.	The Status Report on the CTA: it occurs  ~sep. 2005, that is to say 1 year after the 
CTA proposal. The idea is that at that date we may have all the element to build a 
second generation HORN prototype (CERN prototype is 1st generation) with all the 
drawing, ready to launch the fabrication to be able to get something in 2006.
3.	The  SuperBeam solution report: (end of 2006). After the CTA building and series of 
Test we may be in position to validate the choices to propose a viable solution for 
SPL/Frejus SuperBeam. This allows us to make the final tunig in 2007 to be ready for 
the experiment calendar.
4.	The NuFact solution report (early 2008): the idea is beyond the SuperBeam solution 
we should conclude if the HORN is a viable solution for the NuFact. The CTA and 
other R&Ds (in the world) should be able to answer at the time.
5.	The final report (end 2008) should be the conclusion of the Network Activity with the 
summary of the two solutions (SuperBeam/NuFact).

In the mean while there are dates in 2005 if we need other DS, and they are yearly status 
reports on the: electrical power supply studies, mechanical/thermal studies, irradiated material 
studies. 

Also , there are 2 international workshops TARGET & COLLECTOR:: March 2005 and 
march 2007. Vittorio suggests that these Workshops take place in October rather that March 
which is already crowded, and may be RAL would be the right place. 

What do you think about that? DEAD LINE 7th APRIL evening.

Roger, I invite you to factorise the meeting as I have done and may be the easiest way would 
be to copy and paste my table and add/remove items  to  show specific TARGET items. What 
about the Vottorio suggestion about the Int. Workshops date and place?
 

Cheers,
Jean-Eric